Steel Mill Test Certificates: Check the Heat Number Before Acceptance
Match steel inspection documents to the delivered material, heat identification and purchase specification. A receiving checklist for buyers, not a substitute for technical acceptance.

Short answer
A steel mill test certificate (MTC) is useful only when its inspection information can be connected to the delivered material and checked against the purchase specification. The British Stainless Steel Association (BSSA) advises buyers to check material grade, dimensions and heat number on the material where possible, not just the packing label. For a receiving team, the practical sequence is: identify the material, match its heat or cast reference to the document, then review the document against the order. A familiar grade name or a stamped PDF alone does not complete that check.
Start with the material, not the certificate heading
Bring the purchase order, packing list, inspection document and accessible material identification together. Record the product form, size and grade as ordered, then compare the delivered identification with the document. A heat number links material to a production heat; it is not a grade designation. Do not assume that two bundles with the same section size belong to the same heat.
If a mark is unreadable or the document reference cannot be connected to the material, record the uncertainty rather than filling the gap from a similar bundle. Where material has been cut or repacked, ask how identification was maintained. This is a receiving workflow recommendation, not a promise that every product uses the same marking method.
Check which inspection document was ordered
EN 10204 describes inspection document types; it does not itself select the steel grade or establish the project's acceptance criteria. The British Constructional Steelwork Association (BCSA) explains the distinction between non-specific test reporting and specific inspection results: a Type 2.2 report is not evidence of tests specifically on the supplied material, whereas Type 3.1 inspection certificates report specific test results for the lot from which the products were supplied. BCSA also explains that a Type 3.1 certificate is endorsed by the manufacturer's representative independent of the manufacturing process.
Check the document type actually required by the order. Do not turn a Type 2.2 report into a Type 3.1 certificate by changing its title, and do not treat a Type 3.1 certificate as a product approval or as proof that every test imaginable has been performed. The applicable product standard and purchase requirements determine which results matter. The BCSA note is used here for document definitions, not as a statement of current project-specific code requirements.
A receiving record buyers can use
- Order reference: identify the purchase line and its agreed product standard, grade, delivery condition and document requirement.
- Material link: record the heat or cast identification observed on the material or its traceable identification system, and the matching certificate reference.
- Product match: compare product form, dimensions and quantity with the order and packing information; investigate differences rather than assuming they are administrative.
- Results review: have the responsible technical reviewer compare required chemical and mechanical results with the applicable specification. Do not borrow limits from a similarly named grade.
- Disposition: record acceptance, an open query or a hold, the person responsible for the decision, and the supporting document revision.
This checklist is SHEDAR's suggested way to organise a buyer's receiving query, not a replacement for the purchaser's inspection plan. Keep the original document with the review record; a transcription of selected values loses context.
What to do when the numbers do not match
BSSA recommends verifying the document details, contacting the supplier about discrepancies and keeping records and photographs. If material safety is in doubt, avoid using it until verified. Send the disputed certificate reference, the purchase line and clear identification photographs in one query. Do not edit the certificate to make the mismatch disappear. A missing or inconsistent reference requires clarification; it does not by itself prove fraud or establish the material's properties.
SHEDAR supplies structural steel sourced to order through our established supply channel in China. For a document query on steel products, identify the order and the exact mismatch so the supply documents can be reviewed. Required documents and acceptance criteria should be agreed for the specific order.
Frequently asked questions
Is a heat number the same as a steel grade?
No. A heat number identifies a production heat for traceability; a grade names specified material requirements. Check both against the order and material identification.
Does a Type 3.1 certificate mean every piece was individually tested?
No. Specific inspection results relate to the lot from which the supplied products came. Review the applicable product standard and the ordered inspection requirements.
What should I do if the material marking and certificate do not match?
Record the discrepancy, keep the original documents and identification photographs, and ask the supplier to clarify the link. If safety is in doubt, avoid using the material until verified.
Sources and scope
- BSSA: The Misuse of EN 10204 Material Test Certificates — receiving checks and discrepancies.
- BCSA: Inspection Documents, SN39 — document definitions; not used as current project-code advice.